Rail replace buses over bank holiday due to Knottingley railway bridge work
Rail replace buses will run this weekend as a bridge near Knottingley undergoes hundreds of thousands of pounds of work.
An £800,000 upgrade of a near Knottingley will affect some journeys via Brotherton Bridge over the bank holiday.
Network Rail will renew the track support system across the structure by replacing ageing sections with modern fibre-reinforced components, enabling the continued safe use of this section of line.
Repairs and repainting work will also be carried out on the bridge while scaffolding remains in place.


Also taking place over the bank holiday weekend will be the renewal of 1.4km of track at Sherburn in Elmet.
The work will affect some Northern and TransPennine Express (TPE) journeys in the area from Saturday, August 29 to Monday, August 31, with buses replacing trains between Selby and York/Leeds/Micklefield, and between York and Moorthorpe.
Karen Duffy, Network Rail operations director, said: “Brotherton Bridge is a key piece of railway infrastructure, and these works will see the renewal of waybeams, which support the rails across structures like bridges, alongside essential repairs and repainting.
“Combining this work with track renewal at Sherburn in Elmet allows us to make the best use of the time the railway is closed and deliver improvements that will support smoother, more reliable journeys.
“We’re sorry to anyone whose journey will be affected and appreciate the understanding of passengers while the work is carried out.”
Brotherton Bridge has carried trains across the River Aire since the mid-19th century.
Originally built as a tubular railway bridge during the Victorian era, its superstructure was replaced in 1903 with the steel bridge that still carries trains today.
It is part of a larger viaduct complex with approach arches on either side of the river, making it a significant piece of railway engineering infrastructure.
A spokesperson for Northern and TPE said: “We’re working closely with Network Rail to keep customers moving while these upgrades take place. The work will help improve the reliability of the railway for passengers in the future.