Here's when there will be overnight M62 closures to allow for bridge replacement preparation
and on Freeview 262 or Freely 565
Network Rail is replacing Castleton bridge which carries the main railway line over the M62 between Manchester and Rochdale as part of the Manchester Victoria to Leeds route.
Advertisement
Hide AdAdvertisement
Hide AdThe M62 will be closed in both directions in September for two full weekends when the bridge will be removed and replaced.
Preparation work this month requires five successive overnight closures of the westbound M62 from Monday (July 15).
Next week, the westbound carriageway will be closed nightly between 9pm and 6am between junction 20 of the motorway at Rochdale and junction 19 at Heywood.
Advertisement
Hide AdAdvertisement
Hide AdA clearly signed diversion will be in place with drivers leaving the westbound M62 at junction 20, joining the southbound A627(M) and then using the westbound A664 and northbound A6046 to re-join the M62 at junction 19.
Drivers are being reminded the M62 will be closed in both directions around the clock for two full weekends in September – from 9pm on Friday, September 6 to 6am on Monday, September 9 and from 9pm on Friday, September 20 to 6am on Monday, September 23.
There will also be nightly closures of the motorway in both directions between the two weekend closures.
Advertisement
Hide AdAdvertisement
Hide AdFurther information for drivers, including diversion routes, will be issued nearer the time but National Highways is asking drivers to note the dates and be prepared to delay journeys or use alternative trans-Pennine routes and or modes of transport.